AWPR – A93 Enabling Works – Soil Nails

Client: Transport Scotland

Main Contractor: AWPR CJV

Duration: 4 Weeks

 

Summary of Albion Works:

  • Installation of over 260 No. soil nails
  • Installation of  700m² of Macaferri MacMat R Netting
  • Installation of 420m² of A393 Rigid Mesh
  • Installation of 30No Anchor Drains

As part of the AWPR South Section works, the requirement for soil nails was identified in order to support a temporary excavation adjacent to the existing A93 at Milltimber, thus allowing the construction of a new bridge structure to take place. In partnership with one of our approved design consultants, Albion were able to offer a complete design and build service for the soil nailed slope. The works were completed between June and July of 2016.